Formtech Inc. produces transformers. Each order is custom designed and manufactured for the customer. Each order goes through 3 phases: 1. Transformer Design, which takes 4 weeks. 2. Procurement, which has a lead time of 8 weeks. 3. Assembly and Testing, which takes 4 weeks. The design group can handle only 4 projects at any given time. The other groups are not capacity constrained. Please answer the following: How many projects is Formtech able to complete per year? How much total work-in- process (number of projects started but not yet completed) does the company typically have? (Hint: Little's Law)