Respuesta :
Answer:
It will cost approximately $71.360.
Step-by-step explanation:
Given,
The dimension of the concrete is 17 ft by 17 ft by 2 in.
1 ft = 12 inches ⇒ 2 inches = 1/12 × 2 = 1/6 ft.
Thus, the dimension of the concrete is 17 ft by 17 ft by 1/6 ft.
Now, the volume of the concrete = 17 × 17 × 1/6
[tex]=\frac{289}{6}\text{ cubic ft}[/tex]
We know that,
1 cubic yard = 27 cubic feet
[tex]\implies 1 \text{ cubic feet}=\frac{1}{27}\text{ cubic yards}[/tex]
[tex]\implies \frac{289}{6}\text{ cubic ft}=\frac{289}{6}\times \frac{1}{27} = \frac{289}{162}\text{ cubic yards}[/tex]
Since, the concrete costs $40.00 per cubic yard.
Hence, the total cost of concrete = [tex]\frac{289}{162}\times 40=\frac{11560}{162}=\$71.3580247\approx \$71.360[/tex]