Respuesta :
Answer: To solve, we would need to know how many hours were worked in previous weeks to find out the increase in hours that will give off the 10% increase in total production.
Explanation: To find the production volume increase - subtract the most recent production volume by a previous production volume and then divide that by the previous production volume.
Operations management is the process of business management to increase efficiency to highest possible level
The number of scheduled hours to achieve the goal is 13,591 hours
The parameters of the question that are required are;
[tex]Productivity \ rate = \dfrac{Actual \ Volume }{Actual \ Scheduled \ Hours + Actual \ Overtime Hours}[/tex]
The actual volume for the last 7 days = 584,413
Actual scheduled hours = 12,088
Actual overtime hours = 264
Therefore, we have;
[tex]Productivity \ rate = \dfrac{584,413}{12,088+ 264} \approx 47.3[/tex]
The productivity rate ≈ 47.3 vol./hour
Where there is an increase in volume rate by 10%, we have;
Required volume = 584,413 ×10/100 + 584,413 = 642,854.3
Let x represent the needed scheduled hours to achieve the goal, we have;
[tex]\dfrac{642854.3}{x } \approx 47.3[/tex]
Therefore, x = (642,854.3)/47.3 ≈ 13,591
The number of scheduled hours that need to achieve the goal, x ≈ 13,591 hours
Learn more about operations management here:
https://brainly.com/question/24383464