Answer:
Job cost sheet for Tudor 2 at April 30 is $97,000
Explanation:
When using job order costing all the cost directly related to de order to the order are assigned to it's respective cost sheet. The materials and work used in each particular order can be perfectly identified.
During April materiales used in order Tudor 2 are $85,000
Direct Labor used in order Tudor 2 is $4,800
Overhead is applied at 150% of direct labor cost son it is $4.800*1.5=$7,200
So:
$85,000
+
$4,800
+
$7,200
-------------
$97,000