The assumptions of the production order quantity model are met in a situation where annual demand is 5000 units, setup cost is $40, holding cost is $1 per unit per month, the daily demand rate is 20 and the daily production rate is 100. How long is the cycle length (from the moment that production of a new batch starts until the moment all units are consumed)?
A. 10.2 days.
B. 15.5 days.
C. 11.2 days.
D. 16.5 days.
E. 14.6 days.