Select the correct answer from each drop-down menu. one person working alone will take 30 days to paint an apartment. if d represents the number of days taken to complete the work and p represents the number of people working, the equation that represents this situation is . if 10 people work on this job, they take days to complete it.

Respuesta :

It took 3 days to complete a work by 10 people.

         

What is Efficiency?

The efficiency is the output of the work which we divide by the work input and then express it in a percentage form.

Here, Efficiency of 1 person to complete a piece of work in 30 days is 1/30.

The number of days to complete the work = n days

Number of person to complete the work = p.

Now, according to question

Number of days to complete the work by 10 people = 30 / 10

                                                                                      = 3 days.

Thus, it took 3 days to complete a work by 10 people.

                                                                                       